  • Heat Balance
  • Capacity
  • Pre-Commissioning Checklist

Installation
Foundation
Leveling of Machine
Tube cleaning and replacement space
Chilled water piping as per P & I drawing
Cooling water piping as per P & I drawing
Hot water piping as per P & I drawing
Steam line piping as per P & I drawing
Exhaust piping as per P & I drawing
Flushing of all lines before connecting to the Chiller (By putting Dummy at Chiller flanges)
Chilled water, cooling water pump running and flow rates verified and air bleeding from the system
Hot water pump running and flow rates verified and air bleeding from the system
Strainers in Chilled water and cooling water circuit – cleaned and reinstalled after flushing
Strainers in Hot water circuit – cleaned and reinstalled after flushing
Cooling Tower installation completed, fan rotation and water circulation checked
Cooling water auto shut off valve ( Mandatory, if cooling water pump is not dedicated to the machine )
Installation of Hot water control valve as per P&I
Installation of Steam control valve as per P&I
Installation of Hot water shut off valve as per P&I
Installation of Steam shut off valve as per P&I
Three way by-pass valve provided in cooling water to maintain Inlet temperature
Main supply – Power cable 3 phase, neutral, earth connected to control panel as per E&I drawing
Separate Instrument earth connected to chiller as per E&I drawing
Chilled water pump start/stop permissible connected to machine as per E&I drawing
Chilled water pump feedback connected to machine as per E&I drawing
Cooling water pump start/stop permissible connected to machine as per E&I drawing
Cooling water pump feedback connected to machine as per E&I drawing
Cooling tower start/stop connected to machine as per E&I drawing
Hot water pump start/stop permissible connected to machine as per E&I drawing
Hot water pump feedback connected to machine as per E&I drawing
Hot water control valve connections between valve & machine as per E&I drawing
Steam control valve connections between valve & machine as per E&I drawing
Profibus / Profinet /Modbus connection as per E&I drawing
Nitrogen Pressure in the machine